Deviation report DEV-2026-027
| Project, site or department | Solbacken housing, block C |
| Exactly where | Block C, second floor, flat 2B bathroom |
| Date found | 12 November 2026 |
| Found by | Johan Ek, site supervisor |
| What it concerns | Work or workmanship |
| How serious | Major: affects function, cost or time |
1. What should have been done
Drawing VS-204 and the supplier's instructions require a waterproof membrane up to 200 mm on all bathroom walls.
2. What was found
The membrane reaches only 100 mm on the north wall. Tiling had not started.
Evidence: Photos 1 to 3, tape measurement witnessed by Sara Lind.
3. What was done straight away
Work in the bathroom stopped and the area marked. Subcontractor told the same day.
4. Why it happened
The installer worked from an old drawing. Drawing updates were not sent to the subcontractor.
5. Actions
| Action | Who | By when | Done on |
|---|---|---|---|
| Install membrane to the required height on the north wall | Subcontractor, Ali Demir | 14 November 2026 | |
| Check the other bathrooms in block C | Johan Ek | 15 November 2026 | |
| Send every drawing update to subcontractors on the day of issue | Sara Lind | 20 November 2026 |
6. Effect and who has been told
Effect on cost and time: Two days of rework, paid by the subcontractor. No change to the handover date.
Told: Client's representative, Eva Nyström, 12 November
7. Closing the deviation
☐ The fix has been checked and works
☐ Actions to stop it happening again are done
☐ Records and drawings are updated
Reported by: Johan Ek, site supervisor Signature: ______________ Date: ______________
Checked and closed by: ______________ Signature: ______________ Date: ______________