Project budget
A spreadsheet to plan and follow the cost of a project. List each cost with its estimate, add the actual amount as bills arrive, and see the difference and status of every line, the total, what is left of the approved budget and the headroom after the contingency reserve. Download it as Excel, OpenDocument, PDF or CSV.
Budget
Project budget
Estimate each cost first, then enter the actual amount as bills arrive. Status and totals follow.
Project Office move, second floor
Project manager Daniel Okafor
Approved budget 48,000.00
Contingency reserve (%) 10
| Cost item | Category | Estimate | Actual | Difference | Status |
|---|---|---|---|---|---|
| Movers and van hire | Services | 9,500.00 | 9,200.00 | 300.00 | Under |
| New desks and chairs | Equipment | 16,000.00 | 16,850.00 | -850.00 | Over |
| Network cabling and Wi-Fi | IT | 6,500.00 | 6,100.00 | 400.00 | Under |
| Painting and repairs | Works | 5,200.00 | 5,200.00 | Not started | |
| Signage and printing | Marketing | 1,800.00 | 1,650.00 | 150.00 | Under |
| Cleaning after the move | Services | 900.00 | 900.00 | Not started | |
| Total | 39,900.00 | 33,800.00 | 6,100.00 | ||
| Approved budget | 48,000.00 | ||||
| Contingency reserve | 4,800.00 | ||||
| Estimated cost | 39,900.00 | ||||
| Spent so far | 33,800.00 | ||||
| Left to spend (budget less spent) | 14,200.00 | ||||
| Headroom (budget less reserve less estimate) | 3,300.00 | ||||
| Share of budget spent | 70.4% |