Gantt chart
A Gantt chart in a spreadsheet. List each task with its owner, start date, length in days and the percentage done. The sheet works out the end date of every task, draws a coloured bar for each week the task runs and shows the planned finish of the project and its overall progress, weighted by the length of each task. Download it as Excel, OpenDocument, PDF or CSV.
Gantt
Gantt chart
Enter each task with its start date and length in days. The bars on the right, the end dates and the progress follow.
Project Website relaunch
Project start 2027-03-01
Planned finish 2027-06-02
Overall progress 43% Week starting
| Task | Owner | Start | Days | Done (%) | End | 2027-03-01 |
|---|---|---|---|---|---|---|
| Research and goals | Nadia | 2027-03-01 | 10 | 100 | 2027-03-10 | 1 |
| Sitemap and wireframes | Pedro | 2027-03-08 | 14 | 100 | 2027-03-21 | |
| Visual design | Aiko | 2027-03-22 | 21 | 70 | 2027-04-11 | |
| Content writing | Nadia | 2027-03-15 | 35 | 40 | 2027-04-18 | |
| Development | Pedro | 2027-04-12 | 35 | 10 | 2027-05-16 | |
| Testing and fixes | Lars | 2027-05-17 | 14 | 0 | 2027-05-30 | |
| Launch | Lars | 2027-05-31 | 3 | 0 | 2027-06-02 |