Change order CO-007
Date: 7 November 2026
Project: Harbour View Offices, level 3 fit-out
Contract: Contract HV-104, dated 3 March 2026
Client: Harbour View Properties Ltd, 2 Quay Road, Dublin
Contractor: Doyle Building Services Ltd, 18 Mill Lane, Dublin
1. What changes
Replace the glass partition on grid line C with a fire-rated partition and door set, and add two extra power points in the meeting room.
Asked for by: The client's architect, Niamh Byrne, by site instruction 14
2. Why it changes
The fire engineer's report of 2 October requires a fire-rated wall at this point. The power points are a client request.
3. Cost of the change
| Item | Quantity | Unit price | Tax % | Amount |
|---|---|---|---|---|
| Fire-rated partition and door set | 1 | 6,800.00 | 23% | 6,800.00 |
| Extra power points | 2 | 180.00 | 23% | 360.00 |
| Glass partition no longer needed | 1 | -3,200.00 | 23% | -3,200.00 |
| Subtotal | 3,960.00 |
| Tax 23% | 910.80 |
| Total of this change | 4,870.80 |
4. Contract sum
| Amount | |
|---|---|
| Original contract sum | 420,000.00 |
| Earlier change orders | 12,500.00 |
| New contract sum, with this change | 437,370.80 |
5. Time
Effect on time: 5 working days added
New completion date: 12 February 2027
6. Terms
Once both parties have signed it, this change order forms part of the contract named above. All other terms of that contract stay the same.
The price is valid until 30 November. After that, materials may be re-priced.
Signatures
For the client
Name: ______________
Signature: ______________
Date: ______________
For the contractor
Name: ______________
Signature: ______________
Date: ______________