Test plan
Product: TidyPlan mobile app 4.2.0
Test lead: Anna Berg
Plan version: 1.0, 3 March 2030
1. Objectives
That shared lists work for up to 6 people at once, that login and photo upload no longer crash and that nothing that worked before is broken.
2. Scope
In scope
Shared lists, login, photo upload, notifications, the 20 key user journeys.
Out of scope
Admin web panel, unchanged since 4.1.0. Tested only through the regression pack.
3. Kinds of test
| Test type | Who | When |
|---|---|---|
| Unit tests | Developers | On every change |
| Integration tests | Developers | Daily |
| Manual feature tests | Testers | Per feature |
| Regression pack | Testers | Before release |
| Performance test | Test lead | Once, 500 users at once |
| Security check | Security lead | Once |
4. Environments and devices
Test server with copy of the live setup, without real customer data. 6 phones: 3 Android, 3 iOS, the oldest supported and the newest.
5. Test data
Made-up accounts and lists. No real personal data.
6. Schedule
| Step | Date |
|---|---|
| Test plan agreed | 3 March |
| Feature testing | 3 to 7 March |
| Regression | 8 to 10 March |
| Release decision | 11 March |
7. Bugs
Each bug is logged with steps, screenshot and device. Critical: blocks release, fixed in 1 day. High: fixed before release. Medium and low: planned.
8. Entry rules
The build is on the test server, unit tests pass and release notes exist.
9. Exit rules
All planned tests run. No open critical or high bugs. Regression pack at least 98 percent passed. The test lead signs the report.
10. Risks
Only 2 testers in the final week. Mitigation: developers join regression testing.