Release plan

Plan a software release: scope, dates, testing, rollout, rollback and who tells whom.

Fill it in and preview

Release plan

Product: TidyPlan mobile app
Release: 4.2.0
Release manager: Hamza Idrissi
Planned date: 14 March 2029

1. Goal

Let households share shopping lists in real time, and fix the three most reported crashes.

2. Scope

Included

Shared lists with live updates
Crash fixes for login and photo upload
Updated onboarding screens

Not included

Dark mode moves to 4.3.0.

3. Schedule

Milestone Date
Code freeze 2 March
Regression testing 3 to 7 March
Beta to 5 percent of users 8 March
Full rollout 14 March
Review 21 March

4. Testing and quality gates

The release goes ahead only if these are met.

All automated tests pass. No open critical bugs. Manual test of the 20 key journeys on the 6 main devices.

5. Rollout

1. Release to 5 percent for 48 hours
2. If crash rate stays under 0.5 percent, go to 50 percent
3. Release to everyone

6. Rollback

Switch the feature off with the remote flag within 15 minutes. If the app itself fails, pause the staged rollout and ship 4.2.1 with the fix.

7. Communication

Support gets release notes on 10 March. Customers are told in the app on release day. The team channel gets a status update at each step.

8. Risks

Store review may take up to 3 days, so submit by 9 March.

9. Success checks

Crash-free sessions above 99.5 percent
At least 30 percent of households use shared lists within 4 weeks

Approved by

______________________ Date: ____________

Templates are a careful starting point, not legal advice. Where the law matters, check what applies where you are.

IT and projects

What this template is for

A release plan for shipping software safely. Set scope, schedule, testing, rollout, rollback, communication and success checks. Fill it in, then Word or PDF.

It is free to fill in online, needs no account, and downloads as a Word document or a PDF. See all IT and projects templates

IT and projects

What you fill in

The form asks for 14 details. The document fills itself in as you type.

  • Product

    For example: TidyPlan mobile app

  • Release name or version

    For example: 4.2.0

  • Release manager

    For example: Hamza Idrissi

  • Planned release date

    For example: 14 March 2029

  • Goal of the release

    For example: Let households share shopping lists in real time, and fix the three most reported crashes.

  • What is included

    One item per line.

    For example: Shared lists with live updates Crash fixes for login and photo upload Updated onboarding screens

  • What is not included (optional)optional

    For example: Dark mode moves to 4.3.0.

  • Schedule

    One row for each milestone.

    For example: Code freeze | 2 March Regression testing | 3 to 7 March Beta to 5 percent of users | 8 March Full rollout | 14 March Review | 21 March

  • Testing and quality gates

    For example: All automated tests pass. No open critical bugs. Manual test of the 20 key journeys on the 6 main devices.

  • Rollout steps

    For example: 1. Release to 5 percent for 48 hours 2. If crash rate stays under 0.5 percent, go to 50 percent 3. Release to everyone

  • Rollback plan

    For example: Switch the feature off with the remote flag within 15 minutes. If the app itself fails, pause the staged rollout and ship 4.2.1 with the fix.

  • Communication

    For example: Support gets release notes on 10 March. Customers are told in the app on release day. The team channel gets a status update at each step.

  • Risks (optional)optional

    For example: Store review may take up to 3 days, so submit by 9 March.

  • How we will know it worked

    For example: Crash-free sessions above 99.5 percent At least 30 percent of households use shared lists within 4 weeks

IT and projects

What is inside

The parts of this document, in order.

  1. 11. Goal
  2. 22. Scope
  3. 33. Schedule
  4. 44. Testing and quality gates
  5. 55. Rollout
  6. 66. Rollback
  7. 77. Communication
  8. 88. Risks
  9. 99. Success checks

Templates

How it works

  1. 01

    Fill in

    Type your details in the form. The document fills itself in as you type; click any gap to jump to its field.

  2. 02

    Check

    Read it through. Gaps you have not filled stay marked, so nothing goes out half done.

  3. 03

    Download

    Save it as a Word document to edit further, or as a PDF to send or print.

Make it yours with AI

Open it in the chat and ask for changes: shorter, firmer, another situation, another language.

Adapt it with nerix

IT and projects

Questions people ask

What details does this template ask for?

The form asks for 14 details, starting with Product, Release name or version, Release manager, Planned release date, Goal of the release. 2 more are optional.

Can I download this template as Word or PDF?

Yes. When you have filled in the form, save it as a Word document to keep editing, or as a PDF to send or print. It is free and needs no account.

Is what I type sent anywhere?

No. What you type stays in your browser while you fill in the document. It only goes to nerix if you choose to open the template in the chat.

Are these IT and project templates free?

Most are. Fill in and download them for free as Word or PDF, with no account. A few longer documents are premium: free to fill in, paid once to download, and marked with their price.

Does a security policy make us secure?

No document does that alone. A policy helps when it matches what people really do, so keep it short, explain it to your team and review it every year.

Is a project charter only for large projects?

No. A small project benefits too, because one page that names the goal, the limits and the decision maker prevents most arguments later.