Daily site report
| Project | Riverside Apartments, phase 2 |
| Project number | P-2291 |
| Site address | Kaistrasse 40, Hamburg |
| Date | 16 November 2026 |
| Report number | 87 |
| Prepared by | Stefan Wagner, site manager |
| Weather | Morning rain, dry from 11:00, 6 to 9 degrees, light wind |
| Site open | 07:00 to 16:30 |
1. People on site
| Company or trade | People | Hours | Note |
|---|---|---|---|
| Our own workers | 6 | 48 | |
| Kraus Concrete | 4 | 32 | Second floor slab |
| Müller Electrical | 2 | 16 |
| Total people | 12 |
| Total hours | 96 |
2. Work done today
- Second floor slab: formwork finished and 42 cubic metres of concrete poured in axes A to D.
- Electrical conduits fixed on the first floor.
- Scaffolding raised on the north side.
3. Equipment
| Equipment | Hours used | Note |
|---|---|---|
| Tower crane | 8 | |
| Concrete pump | 3 | Hired for the pour |
4. Deliveries
| What arrived | Supplier | Delivery note | Condition |
|---|---|---|---|
| Concrete, 42 cubic metres | Hanse Beton | DN-58213 | Good |
| Rebar, 2 tonnes | Stahl Nord | DN-1174 | Short by 200 kg |
5. Visitors and inspections
Structural engineer checked the rebar before the pour and approved it at 08:30.
6. Instructions and changes received
Client's representative asked for a change to the balcony door on flat 12. Change order to follow.
7. Delays and problems
Rain stopped the scaffolders until 11:00, about 3 hours lost for 2 people. Short rebar delivery may delay axis E tomorrow.
8. Safety
No injuries or near misses. Toolbox talk on working at height, 12 people attended.
9. Plan for tomorrow
- Strip formwork in axes A and B.
- Fix rebar in axis E once the rest arrives.
- Electricians carry on on the first floor.
Sign-off
Site manager: ______________ Signature: ______________
Client's representative: ______________ Signature: ______________ Date: ______________